Projects

Thames Tideway

Cleaning up the River Thames

Projects

Heading

This is some text inside of a div block.
Thames Tideway — secant pile retaining wall for air treatment chamber
Sector
Client
Thames Tideway
Engineer
Arup-Atkins JV
Contractors
BMB JV
Location
London
Duration
Rigs
see our rigs

The Thames Tideway Tunnel is a 25 km long “super sewer” that aims to clean up the river. Our scope for this substantial scheme included an embedded hard-firm secant pile retaining wall to form the perimeter wall for an air treatment chamber.

We also installed reservation tubes for inclinometers, carried out thermal integrity profile (TIP) testing and provided piling attendances. Finally, we undertook pre-start trials and testing of the proposed concrete mixes, making use of the on-site UKAS accredited testing laboratories operated by BMB JV. 

Thames Tideway — rotary bored piling with segmental casing

Efficiency: Single Visit

Piles, which were 14.5 metres in depth, were completed in a single site visit using our Soilmec SR-75 piling rig. Installation involved rotary bored piling techniques using 880 mm diameter segmental casing.

No items found.
drag

Related projects

see project