Project Information
The increased use of cloud computing has resulted in the proliferation of data centres, a rapidly emerging market sector which is both vital to the health of UK businesses and central to the UK’s digital economy.
Equinix LD7 is the fourth Equinix data centre to be built on the Slough Trading Estate.
Morrisroe Piling was appointed by J Coffey Limited and our work included the design and Installation of 60Nr x 500mm diameter piles, with depths up to 21.8m, and 106Nr x 600mm diameter with depths up to 20.8m. Additionally our scope included the adoption and warranting of 34Nr existing 600mm diameter piles (installed in a previous phase of works) as well as installing two working test piles. The works were undertaken using our Soilmec SR95 piling rig.