Projects

Global Switch

Restricted access within a live data centre

Projects

Heading

This is some text inside of a div block.
Client
Global Switch
Engineer
ARC:ST
Contractors
Sudlows
Location
Tower Hamlets, London
Duration
12 weeks

For Global Switch’s expansion, we were required to work within a live data centre. We installed case and auger piles with restricted access low headroom piles for new columns that were supporting additional load from the data centre.

Different pile diameters were adapted to and installed using both our Klemm 702 and 708 rigs, dependent on the working space that was available to us. Piles were installed within the existing structure and the presence of backfilled dock meant that up to 12 metre deep temporary casings were needed to seal into the London Clay, while operating within restricted headroom.

Additional measures were taken to deal with contaminated soil and ground gases. We encountered various contaminates dating back over 200 years from when it was a busy dock.

Reconfiguring Piles: Tight Working Space

As existing piles and the location of the new columns were very close to existing walls, we needed to reconfigure pile positions. Additional piles at close centres provided the required capacity for the new columns, resulting in tension and compression piles.

No items found.
drag

Related projects

see project